Gurugram metro expansion: 27 new stations, ₹5452.72 crore project
Indiatimes February 05, 2025 01:39 AM

Gurugram Metro Expansion Update: The construction of the Gurugram Metro, a major urban transport project, is most likely to commence on May 1, 2025, as announced by Haryana Chief Minister Nayab Singh Saini. This project will span 28.5 kilometers and feature 27 elevated stations, connecting key areas such as Millennium City Centre, Old Gurugram, and Cyber City. 

The estimated cost for this is ₹5,452.72 crore, with funding contributions of ₹896.19 crore from the central government and ₹4,556.53 crore from the Haryana government. The metro line aims to enhance connectivity and is expected to serve approximately 540,000 passengers daily, with projections suggesting an increase to 726,000 by 2031.

Gurugram Metro Expansion Update

Before construction begins on the Old Gurugram Metro, the width of the route needs to be increased. Habitat Tectonics Architecture and Urbanism Private Limited has suggested this to Gurugram Metro Rail Limited and Haryana Mass Rapid Transport Corporation. The survey report shared by Gurugram Metro Rail Limited highlights that various organisations, including GMDA, NHAI, PWD B&R, and HSIIDC, will work on widening specific sections of the route.

The report indicates that 80.19 km of GMDA, 17.07 km of HSIIDC, 23.34 km of NHAI, 11.57 km of PWD B&R, and 182.27 km of Gurugram Municipal Corporation will be widened. Also, a new 16.69 km route will be constructed to connect with the eco-trail, and a 3.40 km road will also be widened.

Gurugram Metro Project Overview
  • Total Length: The new metro line will span 28.5 kilometers.
  • Number of Stations: The project will include 27 stations, strategically located to serve key areas in Gurugram.
  • Estimated Cost: The total budget for this ambitious project is approximately ₹5452.72 crore.

Gurugram Metro Project: Funding Breakdown

The funding for the Gurugram Metro expansion will come from both the central and state governments:

  • Central Government Contribution: ₹896.19 crore
  • Haryana Government Contribution: ₹4,556.53 crore
Key Features of the Gurugram Metro Expansion

Here is the required Key Features of the Gurugram Metro Expansion listed:

  • Initial Train Configuration: The metro will initially operate with three-coach trains, which are expected to be expanded to six coaches in the future.
  • Technology: The system will utilize Communication-Based Train Control (CBTC) technology, ensuring efficient and safe operations.
  • Maximum Speed: Trains will have a maximum operational speed of 80 km/h.

Gurugram metro: Connectivity Improvements

The new metro line will significantly improve transportation in Gurugram by connecting major locations:

  • Starting Point: Millennium City Centre
  • Key Connections: The line will extend to important areas including the Railway Station, Sector-22, and Cyber City.
Gurugram metro: Infrastructure Developments

As part of the expansion, additional infrastructure will be developed:

  • Underpasses and Flyovers: The project includes the construction of five underpasses and flyovers to facilitate smooth traffic flow during construction and operation.
Gurugram metro: Timeline for Completion

The construction is expected to be completed within a span of four years, targeting full operational status by 2029. This timeline reflects the urgency and importance placed on enhancing Gurugram's public transport system.

The Gurugram Metro expansion represents a major step towards modernizing urban transport in one of India's rapidly growing cities. With significant investment and strategic planning, this project aims to ease traffic congestion. As preparations will most likely begin for construction in May 2025, there will be a positive impact this metro line will have on Gurugram's infrastructure and economy.